How to measure excavation under BESMM4: a worked example

Excavation is usually the first section you measure in substructure, and errors here carry through to earthwork support, disposal and filling. This article walks through a simple example so you can see how each item is built up.

1. Start with the drawings

Before measuring, confirm the existing ground level, the formation level and the foundation layout. Note the type of soil from the site investigation report, because it affects whether earthwork support is required.

2. Site clearance and topsoil

Measure site clearance over the full area of the building plus any working area, in square metres. Topsoil removal is measured to the stated average depth, also as an area.

3. Excavating trenches and pits

Trench excavation for strip foundations is measured in cubic metres, stating the maximum depth range. Use the centreline girth of the walls multiplied by the trench width and depth.

ItemCalculationQuantity
Centreline girth2 × (12.00 + 8.00)40.00 m
Trench excavation40.00 × 0.675 × 1.0027.00 m³
Earthwork support2 × 40.00 × 1.0080.00 m²

4. Disposal and filling

Excavated material is either disposed of off site or kept for backfilling. Measure the volume to be removed by deducting the volume of backfill from the total excavation.

Tip: keep a running "dimension sheet" as you go. It makes checking and later variations much easier.

Want to practise?

Watch the full video walk-through in the Academy, or join the waitlist for the upcoming BESMM4 Measurement Bootcamp, where you will measure a complete building with feedback.

Save time on your next BOQ

Use the BESMM4 BOQ Template Pack, structured and ready to fill in.

See the template